The country’s largest poly-metallic mine in the northern province of Thai Nguyen is set to roll out its first products in several months, according to the Deputy Director General of Nui Phao Mining Company Limited, Vu Hong.

Hong said the construction work on Nui Phao poly-metallic mine at Thai Nguyen’s Dai Tu district has been basically completed three years after the project was started.

The mine, which has a total investment of 500 million USD, will produce around 3.5 million tonnes of tungsten, fluorspar, bismuth, copper and gold a year, 80 percent of which will be exported.

The deputy director general also said the tungsten processing factory at the mine will use the latest technologies from Europe, Canada , the US , Australia and India .

More than 600 households had to relocate to make land for the mine, which is expected to create stable jobs for more than 1,000 local workers.-VNA