The group has asked construction unitsto speed up progress of key projects. Accordingly, it will put into usefive new turbines at both thermo- and hydro-electric power plants withinthis year, which have a combined capacity of 1,656MW.
Meanwhile, five projects will be launched to build three morethermo-electric power plants and expand two hydro-electric power plants,which are expected to add 2,555MW to the group’s total output.
Inaddition to power generation projects, the EVN is accelerating the paceof construction on 192 transmission systems, particularly six keysystems to ensure power supply for the southern region.
According to EVN announcement on March 5, the group’s average poweroutput is estimated at 391 million kWh per day this month.
It generated over 9.4 billion kWh of electricity in February, drivingthe total output in the first two months of 2014 to 19.79 billion kWh,up 5.5 percent from the same period last year.
It also coordinated with the General Department of Irrigation toimplement three times of supplying water from Hoa Binh, Thac Ba andTuyen Quang reservoirs to serve agricultural production in the northernregion.-VNA