Deputy PM Hai and officials of relevant ministries and agencies made afield trip to inspect the progress of the project on December 28.
The contractors have been constructing fundamental facilitiessupporting the 14.5km railway route, between Cat Linh street in theinner Dong Da district and Ha Dong in the outlying Ha Dong district.
They have finished 279 out of 434 bridge buttresses and 70 among 112 posts of the terminals.
During the trip, Deputy PM Hai asked the stakeholders to deploy allmeans to complete the route in September, 2015 and put it into operationin December.
Japan is the main investor of the project, which is expected to aid Hanoi’s integration and economic growth.-VNA