HCM City to speed up public investment disbursement
Ho Chi Minh City's authorities plan to review obstacles to public spending and the speed of fund allocation and disbursement this year.

HCM City (VNS/VNA) - Ho Chi Minh City's authorities plan to review obstacles to public spending and the speed of fund allocation and disbursement this year.
Le Thi Huynh Mai, Director of the Department of Planning and
Investment, said the city spent 24.62 trillion VND (1.06 billion USD) last year,
or only 85 percent of the allocation for public spending.
Transport infrastructure was one of the areas with a low
disbursement rate, she said.
“The disbursement of public expenditure differed every month
with large sums being disbursed during the final months of the year.”
Some projects are yet to complete investment procedures and are
still in the process of finalising costs or extending loan agreements, especially
urban rail projects like the metro line No.1 between Ben Thanh Market in
District 1 and Suoi Tien Theme Park in District 9.
According to a report by the city government to the Ministry of
Transport, the city needs more than 83 trillion VND to execute 19 major traffic
projects this year, but has managed only 35 percent of the amount.
The main reasons for slow disbursement of public investment
include tardy land acquisition for some projects, delayed completion of
administrative procedures and delays in completing investment procedures and
designs.
Besides, many projects are allocated funds that cannot be
disbursed due to problems related to land acquisition and resettlement.
To speed up public spending the city has assigned the responsibility
for the progress of projects to officials, whose performance will also be
assessed by the rate of disbursement.
It will also review and classify projects that face obstacles
related to investment, construction and bidding procedures, land procedures and
site clearance and capital disbursement to promptly work out solutions.
It will also take away funds from projects with low disbursement
rates and transfer them to projects with higher rates.
It requires projects to be completed this year to be sped up
and final checks and payments to be made to contractors.
In the case of those to be completed after 2020, developers have
been told to urge contractors to speed up construction, complete legal
procedures and carry out final checks of completed works to pay the contractors
on time.
For new projects, developers need to prepare design documents
and cost estimates in accordance with regulations, select contractors and
ensure speedy construction, and speed up compensation payment and resettlement.
Developers must submit a feasibility report to competent
authorities for approval in accordance with the Law on Public Investment, the
Construction Law and others.
The Department of Natural Resources and Environment has been
ordered to work with the Ministry of Natural Resources and Environment to speed
up payment of land compensation and resettlement assistance.
Over the years public investment in the city has been
slow, seriously affecting socio-economic development, experts said.
It also causes loss of trust among investors and donors and
national prestige, they said.
It also results in rising costs, they added../.