Initial plans called for the 3.9-km bridge connecting Tay Ho and DongAnh districts to be finished by 2012, but land clearance delays haveobstructed completion of the bridge.
Nhat TanBridge is expected to be the longest cable-stayed bridge in Vietnam. Total capital investment for construction will reach 13,600 billionVND (655 million USD) from Japan 's Official Development Assistance(ODA) and the Vietnamese Government.
The Ministry of Transport's Project Management Unit 85 (PMU) has been assigned to build the bridge.
Vu Quang Dung, a representative of PMU 85 said: "Only 90 percent of land clearance has been completed so far."
Almost of all of the local households agreed to accept the level ofcompensation offered by the People's Committee after it was increased upto one and a half times. Only 32 of 400 total households in the PhuThuong Ward in Tay Ho district are still holding out, Dung said.
The highest compensation level is 30.6 million VND (1,470 USD) persquare metre, said Nguyen Thanh Tinh, chairman of the Phu Thuong WardPeople's Committee.
To ensure projectimplementation, the Ha Noi People's Committee has urged the Tay Hodistrict People's Committee to hand over all required land for theproject to investors before May 30, said Nguyen The Thao, chairman ofthe committee.
Nhat Tan Bridge , one of sevenbridges planned to cross Red River, is expected to shorten travel timefor vehicles travelling from the city centre to Noi BaiInternational Airport. /.