Witha diameter of 15.589 m, a height of 2.816 m, and weighing 1,000 tonnes,it is the heaviest rotor of hydro-electric power plants in Vietnam .
Accordingto the Son La plant management board, the rotor installation will befollowed by a test run of equipment of the plant’s auxiliary systems inSeptember and October.
The first turbine group will undergo a test run from November 15 to 30 before generating power on December 25, 2010 as planned.
The Son La power plant has six turbines designed to have a combined capacity of 2,400 MW.
Asmany as 17,996 households in Son La, Dien Bien and Lai Chau provinceshave relocated to give land to the Son La plant, which has a totalinvestment capital of over 42.47 trillion VND.
The power plan is expected to be completed by 2012./.