LILAMA tries to complete key petrochemical project on schedule hinh anh 1LILAMA workers at the construction site of the Long Son project (Photo: lilama.com.vn)
Hanoi (VNA) - LILAMA Corporation will strive to complete the construction of Long Son Petrochemical Refinery Plant project in the southern province of Ba Ria-Vung Tau on schedule so that its commercial operation could begin in late 2022.

This is one of the key projects in the oil and gas sector with a total investment of more than 5 billion USD. 

The installation of pipelines and electric equipment is expected to be completed by September 2021.

Director of LILAMA’s Long Son project committee Le Hai Long said that as there are five contractors taking part in the project, coordination is a top priority for concerted operation of the components.

LILAMA is responsible for three bidding packages on the installation work of the project. It was assigned to implement steel structures, manufacture and install material pipelines, among others. 

To date, all three packages have met set targets./.