Jakarta (VNA) - PT MRTJakarta will start work on the second phase of the Mass Rapid Transit (MRT)railroad project in March 2020 and aims to complete the construction in 58months.
Jakarta Governor Anies Baswedan said onFebruary 17 that the second phase would begin with the construction of 2.8 kmalong the HI Roundabout to the Hayam Wuruk Harmoni road, Central Jakarta, withtwo stations set to be built, on Jalan MH Thamrin and Monas.
Meanwhile, PT MRT Managing Director WiliamSabandar said that the contract value for the first stage of the second phaseMRT construction with Shimizu-Adhi Karya JB reached 4.5 trillion Rp (329million USD). The project will begin in March 2020 and is targeted forcompletion by December 2024.
The second phase of the MRT project has atotal length of nearly 8km and an investment of around 1.6 billion USD.
The first phase of the project, with alength of 16km and an investment of 17 trillion Rp (1.2 billion USD), was putinto operation in August 2019, connecting the southern area with the centre ofJakarta./.