According to the municipal People’sCommittee, Hanoi intended to complete 22 key infrastructure projectsfrom 2011-2015, but only seven were put into operation, three areroughly completed, seven have only finished their clearance and fivehave yet to begin.
As of June 15, 2015,disbursement for basic infrastructure projects for the year was at 43.6percent, falling behind schedule.
In order tohasten project implementation, the committee asked relevant departmentsand investors to re-examine and allocate capital to ensure progress andquality.
Relevant agencies were asked to resolve problems relating to site clearance and resettlement.-VNA