New solutions needed for urgent power projects

Complicated and time-consuming investment and construction procedures are among the main reasons for the stagnation of urgent power projects, the Ministry of Industry and Trade's Electricity and Renewable Energy Authority has said.

The draft revised electricity law will comprise some provisions to speed up investment in emergency power projects. (Photo: baochinhphu.vn)
The draft revised electricity law will comprise some provisions to speed up investment in emergency power projects. (Photo: baochinhphu.vn)

Hanoi (VNS/VNA) - Complicated and time-consuming investment and construction procedures are among the main reasons for the stagnation of urgent power projects, the Ministry of Industry and Trade's Electricity and Renewable Energy Authority has said.

The authority said that enterprises, especially State-owned ones and their subsidiaries find it difficult to implement power projects as multi-tiered procedures will directly affect the projects' progress.

For power projects using State capital, the overlap in regulations related to many laws from planning and investment to construction laws makes implementation more complicated. That will create significant barriers for investors.

Enterprises also face challenges in capital mobilisation, the authority noted.

To meet the electricity demand with a growth rate of about 10% each year, the annual investment volume in power sources and grids must reach 7.6 billion USD. That places a large financial burden on State-owned economic groups such as Vietnam Electricity (EVN), Vietnam Oil and Gas Group (PetroVietnam), and Vietnam Industry Coal and Mineral Industries Group (Vinacomin).

From 2006 to 2020, the Government issued many decisions to accelerate the construction of urgent power projects. For example, Decision No 1195/QD-TTg in 2005 and Decision No 2414/QD-TTg in 2013 created specific mechanisms to shorten the preparation and implementation time of power projects, ensuring electricity supply for socio-economic development. These policies have created favourable conditions for putting important power projects into operation on time.

Since 2020, although the Construction Law has provisions for emergency power projects, the implementation of these projects has still encountered difficulties due to the lack of a clear legal corridor. The criteria for determining urgent energy security issues have not been specifically regulated, leading to difficulties in applying specific mechanisms for power grid projects.

Amended Electricity Law helps

According to the authority, the draft revised electricity law will have some provisions to speed up investment in emergency power projects.

Under the draft, the Prime Minister will have the right to decide on emergency power projects and assign State-owned enterprises as investors, except for projects using emergency public investment capital under the Law on Public Investment.

Emergency power projects will be exempted from procedures for in-principle investment approval and forest land use purpose conversion, except for those under the decision-making authority of the National Assembly. This helps shorten the time for enterprises to prepare investments and speed up the implementation of important projects.

Investors who implement emergency power projects will be offered many incentives, including government guarantees under the provisions of the Law on Public Debt Management and the right to make all decisions on construction activities.

Having been in effect for nearly 20 years, with four previous amendments, the Electricity Law still faces challenges that the current provisions have yet to fully address. Thus, experts have emphasised the importance of revising the law to align with the Party's energy policies and ensure consistency across the nation’s legal framework.

Economic expert Nguyen Thuong Lang said two key aspects that should be prioritised in the new law are the integration of green standards and smart technology, as well as the updating of management benchmarks.

He underscored the necessity of restructuring the management framework to ensure the successful execution of significant electricity development initiatives, including Power Development Plan VIII, the National Energy Development Plan and the Politburo’s resolution on national energy strategy orientations.

Director of the Clean Energy and Green Growth Research Centre Ha Dang Son said that clarity in legal regulations regarding bidding and auctions, as well as the specific responsibilities of investors in electricity projects, was essential. He also called for clear accountability to address risks and overcome legal obstacles.

The draft Electricity Law includes nine chapters and 119 articles, focusing on key areas such as ensuring national energy security, encouraging renewable energy development, fostering competitive electricity markets and improving safety regulations for electricity usage and infrastructure./.

VNA

See more

Vietnam aims to export 7 million tonnes of rice in 2026 (Photo: VNA)

Vietnam to proactively reduce rice exports from 2026

Do Ha Nam, Chairman of the Vietnam Food Association (VFA), said that 2026 presents numerous difficulties and challenges, and the global supply glut significantly impacts all exporters, including Vietnam.

Vietjet to operate nearly 1,800 additional flights for Lunar New Year peak (Photo: Vietjet Air)

Vietjet adds nearly 1,800 flights for peak Lunar New Year travel

Passengers planning to travel during the Tet peak period are advised to book tickets early to secure suitable flight schedules. They are also encouraged to complete online check-in within 24 hours prior to departure via Vietjet’s website at www.vietjetair.com, the Vietjet mobile application or the VNeID platform, in order to save time at airport check-in counters.

VinFast will provide each university with two electric cars, along with practical equipment and training materials on electric vehicle repair techniques that meet official standards (Photo: VNA)

VinFast collaborates with 30 colleges to standardise training for EV engineers

VinFast will work with leading institutions offering automotive engineering programmes, including the University of Transport and Communications, the Ho Chi Minh City University of Technology, the Hanoi University of Industry and the Hung Yen University of Technology and Education, to implement hands-on training aligned with industry needs.

Illustrative image (Photo: VNA)

E-commerce at turning point as new law sets higher standards in 2026

To propel the digital economy forward, experts said 2026 should be the year of foundational reforms, including standardised identification for sellers and marketers, real-time transparency in product details, enhanced logistics and financial infrastructure, and robust safeguards for authentic value creation.

Illustrative photo (Photo: VNA)

Billion-dollar capital seeks new opportunities in data centre real estate

Ho Chi Minh City is witnessing a strong investment wave in the data centre sector. The city has set up a dedicated task force to support investment procedures for a Hyperscale Data Centre serving AI development, with total investment estimated at around 2 billion USD. The investor consortium includes UAE-based technology company G42, Microsoft, FPT Corporation, VinaCapital, and Viet Thai Group.

Party General Secretary To Lam (C) and Prime Minister Pham Minh Chinh (third from left) and other delegates break ground Vietnam’s first semiconductor chip manufacturing plant (Photo: VNA)

Vietnam launches first semiconductor chip manufacturing plant

The plant, developed by Viettel Group in line with the mission assigned by the Ministry of Defence and based on the government’s resolution, is located on a 27-hectare site within the Hoa Lac High-Tech Park and is expected to serve national industries such as aerospace, telecommunications, Internet of Things (IoT), automotive manufacturing, medical equipment, and automation.

Vietnam’s cashew exports in 2025 are estimated at 766,600 tonnes, generating more than 5.2 billion USD (Photo: VNA)

Cashew sector faces economic efficiency challenge despite high export revenue

Vietnam’s cashew industry has faced a pressing challenge despite an export revenue of over 5 billion USD for the first time in 2025, as this impressive figure has yet to translate into commensurate economic efficiency for exporting enterprises, especially when the industry seeks to ensure that its position as the world’s leading cashew exporter is matched by sustainable profitability.

Deputy Director General of Vietnam National Authority of Tourism Nguyen Thi Hoa Mai (centre) chairs an online meeting on the organisation of ITE HCMC 2026. (Photo: TITC)

International Travel Expo HCM City 2026 set for August

The expo will feature key activities including on-site and online exhibition booths; a digital business-to-business (B2B) buyer–seller matching programme; Vietnam Night; the opening ceremony; programmes for international buyers and media representatives; forums and thematic seminars introducing key source markets and emerging tourism trends; and a tourism consumer festival.

An illustrative image showing a Crystal Bay Airlines plane. (Photo: dantri.com.vn)

New Vietnamese airline takes off with charter capital of 11.4 million USD

According to the company's registration documents, Crystal Bay Airlines Joint Stock Company was established on November 6, 2025, with a charter capital of 300 billion VND (11.4 million USD). The firm operates in 51 business sectors, with its main focus being air passenger transportation.