The Korea Electric Power Corporation (KEPCO) has showed its interests in procedures of investment in the Song Hau 3 thermal power plant, a major project in the Mekong Delta province of Hau Giang.
At a working session with KEPCO representatives on August 19, Chairman of the provincial People’s Committee Tran Cong Chanh pledged to provide the best possible conditions for the investors in the project.
The two-turbine plant, fueled by coal, will have a capacity of 1,200 MW. It is set to cover 57ha in the Phu Huu A concentrated industrial complex in Chau Thanh district.
Several major thermal power plants are under construction in Hau Giang province, including the 1,200 MW Song Hau 1 and the 2,000 MW Song Hau 2.
The three projects are part of the Song Hau Power Centre spreading over 360ha in Chau Thanh district, which was approved by the Government.-VNA
At a working session with KEPCO representatives on August 19, Chairman of the provincial People’s Committee Tran Cong Chanh pledged to provide the best possible conditions for the investors in the project.
The two-turbine plant, fueled by coal, will have a capacity of 1,200 MW. It is set to cover 57ha in the Phu Huu A concentrated industrial complex in Chau Thanh district.
Several major thermal power plants are under construction in Hau Giang province, including the 1,200 MW Song Hau 1 and the 2,000 MW Song Hau 2.
The three projects are part of the Song Hau Power Centre spreading over 360ha in Chau Thanh district, which was approved by the Government.-VNA