HCM City steps up construction of Ben Thanh - Suoi Tien metro line

The Ho Chi Minh City Urban Railway Management Board is accelerating the construction of Ben Thanh - Suoi Tien Urban Railway Line 1 (Metro No. 1), in particular the underground terminals, with a view to putting the line into use in late 2021.
HCM City steps up construction of Ben Thanh - Suoi Tien metro line ảnh 1Construction of the line (Photo: VNA)

HCM City (VNA) - The Ho Chi Minh City Urban Railway Management Board is accelerating the constructionof Ben Thanh - Suoi Tien Urban Railway Line 1 (Metro No. 1), in particularthe underground terminals, with a view to putting the line into use in late2021.

As of May 25, some 72.90 percent of the workload had been completed.

In late April, the architecture on Floor B1 was basicallycompleted.

The 2.05-billion USD line,which runs 19.7 km between District 1 and District 9, is the first of at least sixmetro lines to be built in the city.

Expected to open in thefirst quarter of 2021, the metro line stations will be linked to buses operatingin the vicinity of the line to help people reach the station more easily.

Construction began inAugust 2012 with 14 terminals, including three underground./.

VNA

See more

The small-sized banking group is forecast to have notable deals in changing the stock exchanges in H2 2025. (Photo: VNA)

Small banks forecast to lead growth in H2

The small-sized banking group is expected to have the strongest growth rate of up to 35% thanks to boosting real estate credit from a low base and starting to accelerate bad debt handling.

Aerial view of cleared land and ongoing demolition at the site of HCM City's Metro Line 2 project. (Photo: thesaigontimes.vn)

Vietnam halts use of German ODA loans for HCM City metro line

The first phase of HCM City's Metro Line No. 2, stretching 11.3km with 10 underground and one elevated station, was approved in 2010 with an estimated cost of 26 trillion VND (994 million USD). That figure was revised to nearly 47.9 trillion VND (1.8 billion USD) in 2019 after delays and cost escalations.

Chairman of the Party Central Committee’s Commission for Policies and Strategies Tran Luu Quang (right) meets with President of AES Vietnam Oliver Marquette on July 9, 2025. (Photo: VNA)

Vietnam pledges support for AES investment in green energy

Tran Luu Quang, Chairman of the Party Central Committee’s Commission for Policies and Strategies, praised AES’s investment performance in Vietnam in recent years and welcomed its long-term commitment, particularly in the field of green and clean energy that supports the country's development and energy transition.

Prime Minister Pham Minh Chinh chairs the third meeting of the steering committee for national key railway projects. (Photo: VNA)

PM urges swift, accountable implementation of key railway projects

As head of the steering committee, PM Chinh reiterated the strategic direction outlined in the 13th National Party Congress, which emphasises the need to continue three strategic breakthroughs, with priority given to railway development and starting work on several sections of the North–South high-speed railway, improving transport connectivity with economic zones, industrial parks, seaports, and airports, and accelerating the pace of urban railway projects in Hanoi and Ho Chi Minh City.

Workers produce textile and garment for export. (Illustrative photo: VNA)

Israeli firms step up sourcing from Vietnam

The conflicts have caused serious disruptions to Israel’s external supply chains, leading to greater demand for a wide range of imported goods. As a result, Israeli enterprises are intensifying efforts to diversify sources of supply, including from Vietnam, to meet domestic consumption needs.