The city’s People’s Committee reportedto Deputy Prime Minister Hoang Trung Hai that of that sum, about 1.56billion JPY (15.4 million USD) has been disbursed for the East WestHighway , while the rest went to the first phase of a water environmentimprovement project.
Municipal authorities haveordered the Urban – Civil Works Construction Investment ManagementAuthority to take drastic measures to accelerate the disbursementprogress before August 31, the expiry of loan agreements’ disbursement.
HCM City asked the Deputy PM to instruct authorised ministries to help speed up the disbursement.
The 21.89km East West highway traverses eight districts and includes11 bridges and 8 overpasses. About 65 percent of its 16 trillion VND(760 million USD) investment was financed by Japan’s ODA.-VNA