Hanoi (VNA) – Prime Minister Pham Minh Chinh chaireda meeting on February 4 reviewing the progress of the eastern section of the north-southexpressway project.
Earlier, he made an on-site inspection of the construction of Mai Son – National Highway45 expressway and Nghi Son – Dien Chau expressway, which pass through the provincesof Ninh Binh, Thanh Hoa and Nghe An.
Minister of Transport Nguyen Van The said there are five projects building roads from Ninh Binh to Ha Tinh as part of the eastern section of the north-southexpressway project in the 2017-2020 period, namely Cao Bo – Mai Son, MaiSon – National Highway 45, National Highway 45 – Nghi Son, Nghi Son – Dien Chauand Dien Chau – Bai Vot.
Of them, the Cao Bo – Mai Son expressway was inaugurated as scheduled, the MaiSon – National Highway 45 project has 59 percent completed, the Dien Chau – BaiVot 1.5 percent and the remainder 10-14 percent.
He attributed the delay of the four projects to slow site clearance, investors’ failure toreach credit contracts, limited capacity of several contractors and supply ofconstruction materials.
PM Chinh asked the Transport Ministry to work closely with departmentsand localities to fix existing shortcomings, speed up site clearance, and seekmore qualified consultants.
The Ministry of Natural Resources and Environment was requiredto review regulations related to the management of construction materials to prevent abnormal price hike that cause State asset wastefulness and unhealthy competition.
The PM also called further attention to ensuring lives of relocated householdsand stepping up vaccination campaign for workers of the projects to hasten theirprogress./.