In the firstplan, the new runway will be built at the south of the airport,alongside passenger terminals, an apron, a taxiway and other facilitiesto ensure the airport’s total capacity of 50 million passengers a year.
Thetotal investment cost for this option is estimated at 75.987 trillion(3.5 billion USD), in which 40.8 trillion VND is used for siteclearance.
The second plan is to place the runway to the north while passenger terminals and the apron are placed to the west.
Estimatedexpense of the plan is cut down by half at 38.8 trillion VND (1.78billion USD), in which site clearance makes up 11 trillion VND.
In the third plan, the new runway is also built at the north of the airport alongside supporting facilities.
Thisoption, however, is said to put huge pressure on Vo Van Kiet streetwhen the number of passenger through the airport reaches 50 millionpassengers per year.
According to the CAAV, the second plan is the best option.
Noi Bai International Airport has currently two runways, which are able to accommodate any kind of passenger plane.-VNA