Resumption of railway project remains in doubt

The Yen Vien – Pha Lai – Ha Long – Cai Lan railway project are waiting for a final decision on whether it would continue to be implemented not.
The date of completion of the Yen Vien – Cai Lan railway project remains in question due to the lack of funding from the State budget (Photo: VietnamPlus)
The date of completion of the Yen Vien – Cai Lan railway project remains in question due to the lack of funding from the State budget (Photo: VietnamPlus)

Hanoi (VNA) - Although trillions of VND sourced from Government bonds was earmarked, 15 years after the start of its construction, the Yen Vien – Pha Lai – Ha Long – Cai Lan railway project remains uncompleted.

Hai Duong and Quang Ninh provinces, where the rail line is set to traverse, repeatedly asked for this project to be resumed and completed as soon as possible, or the ground previously prepared for construction to be returned to local residents if it is cancelled.

Trillions of VND lies idle, residents live in uncertainty due to railway project

The Yen Vien – Pha Lai – Ha Long – Cai Lan railway project, approved by the Prime Minister in Document No. 75/CP-CN dated January 9, 2004, will have a total length of 131km, including 43km of new rail tracks and 88km of upgraded existing tracks, from Yen Vien Station in Hanoi to Cai Lan Terminal in Quang Ninh province. This project is divided into four sub-projects and had its construction started in 2005.

The project has the total investment of 7.665 trillion VND funded by Government bonds. When the route is put into operation, trains from Yen Vien will no longer have to transit in Kep Station of Bac Giang province before moving to Ha Long, which takes 7.5 hours, like at present. Instead, the travel time between Yen Vien and Ha Long will be cut down to 1.5 – 2 hours for passenger trains and 3 – 4 hours for cargo trains.

This project was initially expected to be completed in 2011, but it remains unfinished and has been suspended under the Government’s Resolution No. 11/2011/NQ-CP on public investment reduction. Many of its items like construction materials and equipment worth hundreds of billions of VND have stayed idle for years but they are also unable to be liquidated to recover money for the State budget as the project has not been completed yet.

[Railway sector targets stronger development amid policy difficulties]

In a document sent to the Ministry of Transport, voters in Quang Ninh province said the project, which has been left unfinished and lagged behind schedule for many years, has caused land wastefulness, affected local socio-economic development and led to multiple problems for residents in the areas zoned for the project.

Over the past years, local residents have neither been allowed to build, repair or transfer houses and land, nor compensated or relocated. Statistics showed that there are 3,616 households affected by this project in Quang Ninh. So far, the Transport Ministry has provided 106.28 billion VND to cover site clearance, and the remaining sum needed for this task is around 145 billion VND.

Meanwhile, voters in Hai Duong also complained to the ministry about the Pha Lai – Ha Long rail route, which began 15 years ago but was suspended, cutting off roads, canals and dividing farmland. They urged that this project be resumed and finished as soon as possible, or ground previously prepared for construction to be returned to local residents if it is cancelled.

Solutions to project needed

Concerned about the project’s facilities lying idle and getting dilapidated, the Ministry of Transport has proposed the Prime Minister allow using tracks, sleepers and related equipment purchased under this project for upgrading the Hanoi – Ho Chi Minh City rail route.

However, the Ministry of Finance and the Ministry of Planning and Investment said according to the law on management and use of public asserts, the materials and equipment are public assets and can only be liquidated once the project is completed. Therefore, they are still left unused and getting dilapidated.

Earlier, the Transport Ministry estimated that in order to continue, this railway project will need an additional 6 trillion VND apart from the earmarked 4.556 trillion VND. As a result, the total investment has risen to 10.556 trillion VND from the 7.665 trillion VND approved in 2004. This ministry blamed higher material, labour and site clearance expenses for the increase.

Recently, Deputy Prime Minister Trinh Dinh Dung asked the Transport Ministry to consider the Finance Ministry’s opinions and promptly submit a report to competent agencies so as to decide whether or not this project should be continued.

[Video: Thong Nhat train: The railway line that connects Vietnam]

Deputy Minister of Transport Nguyen Ngoc Dong said this project was suspended in 2011 and reviewed in 2015, noting that his ministry also proposed capital for this project be sourced from the medium-term capital plan for the 2016 – 2020 period, but funding sources weren’t ready so the project has yet to be resumed.

As the Government recently requested this project to be reviewed, the ministry has assigned its strategy institute and the railway project management board to calculate the capital demand so that the Government can consider capital sources and report the issue to the National Assembly at the parliament’s session later this year.

If everything goes smoothly, funding can be sourced from the capital plan for 2021 – 2025 and the project will go ahead, he added./.

VNA

See more

Vice Chairman of the Hanoi People’s Committee hands over investment policy approval for Moscow House project in Hanoi to the Moscow authorities. (Photo published by VNA)

Hanoi, Russian localities step up cooperation in urban railways, technology

Secretary of the Hanoi Party Committee Tran Duc Thang and the delegation held talks with Moscow authorities to review implementation of the 2025-2027 cooperation programme and discuss key priorities for the new period, including urban transport, science and technology, digital transformation, trade and investment, and cultural exchanges.

Vietnamese Ambassador to Mexico Nguyen Van Hai (fourth from right) and others attend the seventh Veracruz International Energy Congress. (Photo: VNA)

Vietnam, Mexico strengthen energy, port cooperation

A number of Mexican state Veracruz businesses expressed their wish to organise a delegation to Vietnam to gain first-hand insights into the market, seek partners and explore investment and business opportunities, initially focusing on trade, energy, agriculture and tourism.

At the working session (Photo: VNA)

Can Tho, Guangxi seek collaboration in logistics, supply chains

Chinese investors now back 35 projects in Can Tho with registered capital of nearly 1.2 billion USD. In the first seven months of 2026, Can Tho’s exports to China hit 77.5 million USD, while imports stood at 64.7 million USD. Key exports included rice, seafood, farm produce, processed agricultural products and apparel while main imports comprised agricultural chemicals, veterinary medicines, fertilisers, chemicals, fabrics and other materials and inputs.

Vietnamese Minister of Finance Ngo Van Tuan grants an interview to the Vietnam News Agency (VNA). (Photo: VNA)

Vietnam, Russia move to boost financial cooperation

On bilateral economic, trade and investment ties, Tuan said two-way trade hit 3.24 billion USD in the first seven months of 2026, up 12% from a year earlier. Vietnam’s exports to Russia totaled 1.33 billion USD, while imports amounted to 1.91 billion USD.

Cai Mep - Thi Vai Port complex in Ho Chi Minh City (Photo: VNA)

Ho Chi Minh City seeks to make seaports new growth driver

To maximise its seaport advantages, Ho Chi Minh City is developing smart and green ports while promoting clean energy, lower emissions and sustainable supply chains. It aims to establish an integrated ecosystem linking seaports with industrial parks, logistics centres, free trade zones, multimodal transport networks and an international financial centre.

Farmers visit the off-season durian orchard of Cao Chi Dai in Vinh Hanh commune, An Giang province (Photo: VNA)

Vietnam promotes finance for green agriculture

Over the past five years, Vietnam has developed and gradually implemented a green finance system to support low-emission and environmentally friendly production, including agriculture. Based on the State Bank of Vietnam's Directive No. 03/CT-NHNN dated March 24, 2015, banks including BIDV, VCB, HDBank and Agribank have introduced green credit packages for waste treatment, high-tech agriculture, digital transformation, regional linkages and emission reduction across production chains.

An overview of the meeting between representatives from Polish businesses and the Agency for Domestic Market Surveillance and Development. (Photo: Agency for Domestic Market Surveillance and Development)

Polish businesses seek suppliers, partners in Vietnam

MAJAMI, a confectionery manufacturer and trader under Sweet House, is seeking distributors for Polish confectionery products in the Vietnamese market. Meanwhile, GABONA, a distributor and wholesaler of professional cosmetics, hair care and make-up products and beauty accessories, is looking for Vietnamese manufacturers of vegan and natural cosmetics.