The inspection was carried out following a complaint by Luong Xuan Binh, formerdeputy head of the Hanoi Urban Railway Management Board.
The inspectorate found grounds for a lot of the issues Binh raised.
The project is developed by Hanoi Urban Railway Management Board. Frenchconsultancy firm Systra was hired for 10.6 million euros in November 2007.
There were many shortcomings in the beginning and the contract contains a lotof ambiguous contents that can be interpreted differently by both parties.
The GI said although the project is complex and large with the application ofnew technologies and standards, the contract only defines a period of 25 monthswith a total value of 10.6 million euros. It is not feasible, failing to meetthe project's requirements.
Three appendices later were signed and the total consulting rate increased to17.1 million euros.
The adjustment of the contract value was attributed to slow progress inperforming the tasks of Systra, causing costs to rise, the GI said.
During negotiation for the adjustment of the consulting contract, the investordid not clarify the responsibility of Systra in the project’s delay todetermine the expenditure and reducing cost when calculating an additional estimatecost.
Regarding the bidding package for unexploded ordnance and mine clearance by theLung Lo Construction Company, violations were also found in the evaluation andpayment process.
The monitoring work was lax and reports were not up to quality standards. Italso failed to comply with the approved plans. The GI said the Engineering HighCommand, the Lung Lo Construction Company and the unit who carry out thebidding package should be held accountable.
The inspectorate suggested the Ministry of Defence review responsibilities inmember agencies over the bidding package.
Violations have also been detected relating the selection of contractors forbidding package No 3, the tunnel and underground stations, according to the GI.
The contractor and the Hanoi Urban Railway Management Board signed a contractto implement package 3 when site clearance for construction was not completed.Currently, planning for stations No 9, 10 and 11 is being adjusted, resultingin the fact that land designated for the project couldn’t be handed over to thecontractor.
The inspectorate said that the delay in handing over the site led thecontractor to adjust the implementation plan and require additional funding ofabout 40 million USD, causing damage to the State budget.
The project has a total length of 12.5km, with an 8.5km elevated track and a 4kmunderground track. The initial cost was estimated at 911 million USD, but thathas risen to 1.3 billion VND.
The project, which kicked off in September 2010, was scheduled to be completedin September 2017 but has had problems with land clearance, so the cityPeople’s Committee extended the project deadline to 2022.
The 8.5km elevated section is planned to be finished in April 2021, with theremaining 4km underground line to be opened in December 2022.
The urban railway line No 3, connecting Nhon area and Hanoi Station, will runthrough Nam Tu Liem, Bac Tu Liem, Cau Giay, Ba Dinh, Dong Da and Hoan Kiemdistricts./.