Launched in December 2022, the shared infrastructure component of the Lien Chieu port project has a total investment of over 3.4 trillion VND (128.9 million USD) and is now 95% complete. (Photo: VNA)
Launched in December 2022, the shared infrastructure component of the Lien Chieu port project has a total investment of over 3.4 trillion VND (128.9 million USD) and is now 95% complete. (Photo: VNA)
The project constructs a 1,170m-long breakwater and seawall. This component is now 96.64% complete (Photo: VNA)
The project constructs a 1,170m-long breakwater and seawall. This component is now 96.64% complete (Photo: VNA)
The seawall section is 573m long and the breakwater section is 597m long. (Photo: VNA)
The seawall section is 573m long and the breakwater section is 597m long. (Photo: VNA)
Construction of the navigation channel and basin is underway, with the channel stretching around 7.3km. This component is now 99.09% complete (Photo: VNA)
Construction of the navigation channel and basin is underway, with the channel stretching around 7.3km. This component is now 99.09% complete (Photo: VNA)
The port’s connecting road consists of two sections with eight lanes. (Photo: VNA)
The port’s connecting road consists of two sections with eight lanes. (Photo: VNA)
The connecting road and supporting infrastructure, including electricity and water supply, are progressing and now 80.17% complete. (Photo: VNA)
The connecting road and supporting infrastructure, including electricity and water supply, are progressing and now 80.17% complete. (Photo: VNA)
The coastal road connecting Lien Chieu port is launched in September 2023, with a total investment of more than 1.2 trillion VND (45.5 million USD) and an overall length of nearly 3km. (Photo: VNA)
The coastal road connecting Lien Chieu port is launched in September 2023, with a total investment of more than 1.2 trillion VND (45.5 million USD) and an overall length of nearly 3km. (Photo: VNA)
The concrete pillars forming the corridor supporting the elevated road. (Photo: VNA
The concrete pillars forming the corridor supporting the elevated road. (Photo: VNA
Looking from below, the elevated road curves gracefully like a rainbow. (Photo: VNA)
Looking from below, the elevated road curves gracefully like a rainbow. (Photo: VNA)
Workers are urgently asphalt-paving the road surface, which is designed with six lanes and a width of 30m. In the photo: Workers cheerfully prepare to finish their shift. (Photo: VNA)
Workers are urgently asphalt-paving the road surface, which is designed with six lanes and a width of 30m. In the photo: Workers cheerfully prepare to finish their shift. (Photo: VNA)
The coastal road connecting Lien Chieu port now reaches 82.30% completion. In the photo is the grade-separated overpass at the Hai Van-South bypass intersection, ensuring independent and non-conflicting traffic flows for vehicles entering and leaving the port. (Photo: VNA)
The coastal road connecting Lien Chieu port now reaches 82.30% completion. In the photo is the grade-separated overpass at the Hai Van-South bypass intersection, ensuring independent and non-conflicting traffic flows for vehicles entering and leaving the port. (Photo: VNA)
0
1
2
3
4
5
6
7
8
9
10

Lien Chieu port - the largest in central Vietnam taking shape

The construction site of Lien Chieu port in Da Nang city is entering the final stage, with more than 95% of the workload completed. Major components are taking shape, revealing the appearance of what will be the largest seaport in central Vietnam, invested by Da Nang’s Priority Infrastructure Investment Project Management Board.