The Construction Joint Stock Company 47 has announced that it had recently reached a deal with Song Da 5 Joint Stock Company to construct the Nam Pha, Nam Phak and Phouphong dams at the Nam Phak hydropower project in Laos.

The Construction Joint Stock Company 47 has recently reached a deal with Song Da 5 Joint Stock Company to construct hydropower dams in Laos. (Photo: VNA)

Hanoi (VNA) - The Construction Joint Stock Company 47 has announcedthat it had recently reached a deal with Song Da 5 Joint Stock Company toconstruct the Nam Pha, Nam Phak and Phouphong dams at the Nam Phak hydropowerproject in Laos.

Thetwo sides signed two contracts, including the one for construction of the damsat Nam Pha, Nam Phak and Phouphong, and the other for the designand testing serving the construction of the Nam Phak hydropower project, with totalcapital of nearly 800 billion VND (34.2 million USD).

The contracts are to take 1,458 days to be completed.

TheNam Phak hydropower project has a total installed capacity of 128 MW. It islocated in the southwest of Bolaven Plateau in Champasak province./.