All parties concerned should be consulted andtheir opinions taken into account before the report is submitted to thePrime Minister on August 20, the Deputy PM said on Aug. 11.
He advised that ministries of Planning and Investment and Transport aswell as relevant agencies petition the PM for establishing a StateAssessment Council to examine the investment report.
Underan approved master plan officially made pubic last August, the airportwill be built in Dong Nai Province's Long Thanh District, some40km northeast of Ho Chi Minh City.
The new airportwill function as an entrepot in the Southeast Asian region, able tohandle 100 million passengers and 5 million tonnes of cargo a year by2030.
The 5000ha airport will also have the capacity to allow massive jumbo jets like the A380-800 to land and take off.
Preparatory works for the country's biggest airport, includingfinancial arrangements, are already underway. The Southern AirportCorporation is in charge of the project development.
Construction of the airport is scheduled to start in 2015 and completed in three phases.
The first phase, carried out between 2015 and 2020, will involve aninvestment of 6.74 billion USD. At the end of this phase, the airportwill be able to handle 25 million passengers and 1.2 million tonnes ofcargo every year.
At the end of the second phase theairport will have three runways and the ability to handle 50 millionpassengers and 1.5 million tonnes of cargo.
When the finalphase is complete, it will have four runways and four terminals withthe targeted capacity of handling 100 million passengers and 5 milliontonnes of cargo per annum.
The plan also envisages thatthe Long Thanh International Airport will be connected to HCMCity and other neighbouring provinces by a network of highways andexpress railway routes, some already under construction.-VNA