First HCM City metro line to get tracks next month

Progress on the first metro line in Ho Chi Minh City continues, but a tax dispute has left some necessary equipment languishing at port, Le Nguyen Minh Quang.
First HCM City metro line to get tracks next month ảnh 1An elevated section of HCM City’s Ben Thanh-Suoi Tien metro line runs along the Hanoi Highway. (Source: VNA)

HCM City(VNA) – Progress on the first metro line in Ho Chi Minh City continues, but atax dispute has left some necessary equipment languishing at port, Le NguyenMinh Quang, head of the HCM City Management Authority for Urban Railways told apress briefing recently.

The elevated sections of the Ben Thanh-Suoi Tien metro line from Ba Sonterminal to Long Binh maintenance depot will install tracks next month, Quangsaid, adding nearly 70 percent of the metro’s elevated sections have beencompleted.

He added that the installation of tracks would be carried out on the completedsections simultaneously with the building of the uncompleted ones.

Equipment used for metro track installation, however, is now “stuck” at port,he added.

He said that previously the Ministry of Finance had announced a zero percenttax rate on imported equipment and goods used for the construction of themetro, but recently it has reconsidered this tax policy, so a new shipment ofequipment remains in its port of entry.

“The HCM City People’s Committee has worked with the city’s Customs Departmentand the General Department of Customs to find a solution to the problem so thatthe construction schedule will stay on track,” he said.

According to Duong Huu Hoa, Director of the Metro Line 1 project, Japanesecontractors are working on the train for the city’s first metro line and willsend it to Vietnam by October next year for early testing.

He said he has sought the opinions of foreign experts on the construction ofthe Dien Bien Phu flyover, one of the five of its kind on the metro route, tominimize the impact on traffic.

The other four overpasses are being built above the Hanoi Highway, the SaigonRiver, the Rach Chiec Canal and Van Thanh Canal.

Regarding the shortage of ODA capital for the metro, Quang said last month thatthe city had to withdraw 500 billion VND (22 million USD) from its budget topay debts to contractors, but that this could not be considered a long-termsolution.

“This is just a temporary solution as in reality the city needs 500 billion-600billion VND a month to pay the contractors,” he said.

The city is looking forward to receiving ODA capital from the central budget inthe medium term from 2016 to 2020 to pay for consulting companies andcontractors this year, he said.

The Ben Thanh-Suoi Tien metro, whose construction began in August 2012, isvalued at 2.49 billion USD. The nearly 20-km metro is expected to beoperational in 2020.-VNA 
VNA

See more

Representatives from industry associations share insights on Vietnam’s market trends. (Photo: VNA)

Vietnam, Thailand boost industrial trade exchange

Trade between Vietnam and Thailand reached 20.18 billion USD in 2024, up 6.4% year-on-year. Thailand remained Vietnam’s top ASEAN trade partner, accounting for 24% of its total trade with the bloc.

Representatives from Lao and Vietnamese agencies at the signing ceremony. (Photo: VNA)

Vietnam, Laos strengthen energy cooperation

A 1,200 MW wind power plant in Nong district, Laos’ Savannakhet province is expected to export 1,526 kWh to Vietnam annually once its first phase completes by the end of 2027, and additionally 1,112 million kWh per year after its second phase becomes operational in 2030./

A view of the Hanoi skyline. While rental properties continue to be in demand, there has also been a notable rise in the number of foreigners looking to buy houses. (Photo: VNA)

Housing demand from foreigners in Hanoi rises

Over several years, Hanoi has increasingly become an attractive destination for foreign workers, with approximately 10,000 new foreign workers are granted licences to work in the city each year.

A high-tech corn, sorghum and grass farm in Nghe An province (Photo: VNA)

Realising circular economy to achieve sustainable development goals

Developing a circular economy has been recognised as one of the priority directions to achieve overarching goals such as waste management, efficient resources utilisation, environmental protection, disaster prevention, and climate change adaptation in the country's next development phase.

National Highway 61C (Photo; baohaugiang.com.vn)

Hau Giang, JICA to upgrade national highway

National Highway 61C linking Can Tho city with Hau Giang province will feature four lanes for motor vehicles and two for non-motorized traffic, with an estimated cost of over 5.17 trillion VND (206.8 million USD).

At the ceremony (Photo: nhandan.vn)

Ha Nam grants investment certificates for two key projects

Ha Nam province on February 13 licenced the high-precision circuit board manufacturing plant of Red Board Technology (Vietnam) Co., Ltd., and the kitchenware and related metal products manufacturing plant of Casla Kitchenware JSC.