Dong Nai to speed up site clearance for Long Thanh airport project

Dong Nai province’s authorities plan to speed up capital disbursement, as well as site clearance, compensation and resettlement for affected households, so that construction of Long Thanh International Airport can begin this year.
Dong Nai to speed up site clearance for Long Thanh airport project ảnh 1Long Thanh International Airport is a key national project that will have a significant impact on the southern key economic region as well as Dong Nai province. (Source: VNA)

Dong Nai (VNS/VNA) -
DongNai province’s authorities plan to speed up capital disbursement, as well assite clearance, compensation and resettlement for affected households, so thatconstruction of Long Thanh International Airport can begin this year.

According to the provincialPeople’s Committee, in the 2018-2019 period, the central government allocated 11.49trillion VND (490 million USD) to the province to implement the project.

The province had disbursed 1.17trillion VND (50.1 million USD) as of January, accounting for 10.24 percent ofthe estimate. The province said it would accelerate the disbursement of theremaining capital by the end of this year.

Dong Nai authorities have askedthe Prime Minister for permission to start bomb and mine clearance in the areato expedite progress of the project.

Speaking at a recent meetingwith Dong Nai authorities, Deputy Minister of Transport Le Anh Tuan said thesite must be available no later than August so that the first constructionphase can begin this year. Opening is expected by 2025.

The province said it hadalready paid compensation to Dong Nai Rubber Corporation to build two householdresettlement areas in Loc An and Binh Son communes in Long Thanh district.

The corporation has beguncutting rubber trees to hand over a clean site, according to the provincial People’sCommittee.

The Long Thanh InternationalAirport is a key national project that will have a significant impact on thesouthern key economic region as well as Dong Nai province, according to Tuan.

He suggested that the Ministryof Transport closely work with Dong Nai province to promptly solve problems toensure that the project remains on schedule.

To build the airport, siteclearance is needed for more than 5,000 hectares of land and more than 364additional hectares to build two resettlement sites, including Loc An – Binh Soncovering 282ha and Binh Son with more than 81ha.

As a result, some 4,800 localhouseholds and 26 organisations are expected to be relocated. Some 70 percentof the 15,500 affected people are farmers, and the rest are rubber plantationworkers and workers in other sectors.

The feasibility study for theairport project has been approved by the Government.

Once fully operational, Long Thanhairport will reduce the load on Tan Son Nhat International Airport in HCM City.

The Long Thanh InternationalAirport is expected to handle 100 million passengers and five million tonnes offreight each year.

Covering a total area of morethan 5,580 hectares, the airport will be located in six communes in Long Thanhdistrict in Dong Nai province.

The airport’s total investmentis 336.63 trillion VND (14.35 billion USD), with construction divided intothree phases.

In the first phase, a runwayand one passenger terminal along with other support works will be built toserve 25 million passengers and 1.2 million tonnes of cargo each year.

The first phase is expected tobe completed by 2025./.
VNA

See more

Hyundai Thanh Cong automobile manufacturing and assembly plant in Ninh Binh province. (Photo: VNA)

Vietnam reports 95% jump in January auto sales

Passenger cars accounted for the lion’s share of the gain, with 26,102 units sold. Commercial vehicles contributed 10,312 units, while special-purpose vehicles totaled 461 units.

The forest database will be completed by the end of this year, adapting to the EU Deforestation Regulation (Photo: VNA)

Forest databases for EUDR implementation to be completed in 2026

Localities nationwide are required to complete the development and publication of provincial-level forest boundary databases and maps as of December 31, 2020, by the end of this year, as part of Vietnam’s efforts to adapt to the EU Deforestation Regulation (EUDR).

PM Pham Minh Chinh announces the establishment of the Vietnam International Financial Centre in Ho Chi Minh City. (Photo: VNA)

PM announces launch of Vietnam Int'l Financial Centre in Ho Chi Minh City

The Vietnam International Financial Center in Ho Chi Minh City and Da Nang will gradually assert Vietnam's position on the global financial map and make a substantial contribution to achieving the 2-digit growth target set by the 14th National Party Congress in the coming years, towards realising the 100-year strategic goals, said PM Pham Minh Chinh.

Duong Thi Lap's garden has 200 kumquat trees ready for Tet (Photo: VNA)

Tet bloom markets: rising demand, stable prices

Across Vietnam, key farming hubs for flowers and ornamental plants are buzzing with activity as the Lunar New Year (Tet) approaches, with farmers robust plant health, eye-catching designs, surging consumer demand, and broadly stable pricing.

Retail sales of goods in January estimated at 487.4 trillion VND (Photo: VNA)

Total retail sales of goods, service revenue up 9.3% in January

Retail sales of goods in January was estimated at 487.4 trillion VND, accounting for the largest share and increasing 9.3% year-on-year. Growth was driven by many categories, including household appliances and equipment, which rose 9.4% thanks to early-year shopping demand and promotional programmes by retailers.

Fishing vessel monitoring system (VMS). (Illustrative photo: VNA)

Quang Tri backs VMS subscription fees for fishing vessels

Under a recently approved provincial resolution, the support will be disbursed once a year. Total funding for the three-year programme is estimated at more than 12.2 billion VND from the provincial budget, benefiting around 1,360 vessels across the province.

Delegates at the meeting in Hanoi on February 9, 2026. (Photo baotintuc.vn)

Vietnam to release 2026 economic census data seven months earlier

Nguyen Thi Huong, head of the Standing Group of the Steering Committee of the 2026 Economic Census and Director of the National Statistics Office (NSO), said the first phase of data collection was underway nationwide and was scheduled to conclude on March 10.

At Xa Mat international border gate (Photo: VNA)

📝OP-ED: Decree 46 - Not proof of distorted “systemic failure”

Temporary suspensions, adjustments, or revisions of newly enacted policies are never ideal and should be minimised. Yet such course corrections occur worldwide, irrespective of a country's development stage or market-economy maturity. What counts is rapid remediation to contain losses, extraction of lessons to prevent recurrence, and firm resistance to the dissemination of misleading or hostile allegations, which will help both enforcers and those subject to compliance maintain clarity and composure.

Delegates at the signing ceremony of the MoU between the Brazil–Vietnam Chamber of Commerce (BVC) and the Espirito Santo Chapter of the Brazil–Vietnam Chamber of Commerce and Industry (CCBV-ES). (Photo courtesy of the Vietnamese Embassy in Brazil)

Vietnam, Brazil step up trade promotion cooperation

The Brazil–Vietnam Chamber of Commerce (BVC) and the Espirito Santo Chapter of the Brazil–Vietnam Chamber of Commerce and Industry (CCBV-ES) recently inked the MoU to enhance cooperation and expand business opportunities for enterprises from the two countries, with support from the Vietnamese Embassy in Brazil.