Problems must be settled for Long Thanh airport construction: PM

Prime Minister Pham Minh Chinh on January 29 asked the southern province of Dong Nai to complete the handover of cleared ground for the first-stage construction of Long Thanh international airport by the end of this first quarter.
Problems must be settled for Long Thanh airport construction: PM ảnh 1PM Pham Minh Chinh inspects progress of the project (Photo: VNA)

Dong Nai (VNA) – Prime Minister Pham Minh Chinh on January 29 asked the southern province of Dong Nai to complete the handover of cleared groundfor the first-stage construction of Long Thanh international airport by the end of this first quarter. 

During a working session with ministries,agencies, localities and stakeholders of the project aftermaking a fact-finding trip earlier the same day to the construction site, he assigned them to responsibility for the work under their watch and solve existing issues.

The Government has directed the establishment of a working groupled by Deputy Prime Minister Tran Hong Ha to oversee and speed up the project,PM Chinh revealed.

At the construction site, he asked ministries, agencies,localities and investor to hasten the implementation of the project, with qualityguaranteed.

Covering a total area of more than 5,580hectares, the Long Thanh international airport will spread across six communesin Long Thanh district, Dong Nai province. The airport’s total investment is336.63 trillion VND (14.6 billion USD), with construction divided into threephases.

In the first phase, arunway and one passenger terminal along with other supporting facilities willbe built at a cost of 109.112 trillion VND to serve 25 million passengers and1.2 million tonnes of cargo each year.

The project started in 2021. Once fully completedby 2050, the airport will be able to handle 100 million passengers and 5million tonnes of cargo annually.

Located 40km east of Ho Chi Minh City, theairport is expected to relieve overloading at Tan Son Nhat internationalairport in the southern metropolis, now the country’s largest airport./.

VNA

See more

Petrovsky Palace in Moscow shines in the golden hues of autumn. (Photo: VNA)

Russia waives visa requirements for Vietnamese tourists

According to a notice published on the official website of Russia’s Ministry of Justice, Vietnamese citizens can now stay in Russia for up to 30 consecutive days, provided their purpose of travel is not employment.

Students from the VACEO art class perform at the Cultural Fusion - Narellan festival. (Photo: VNA)

Vietnamese in Australia keep heritage alive

Vietnamese dance and traditional music classes organised by the Viet-Aus Culture Exchange Organisation (VACEO) have been held every Saturday afternoon in Bankstown, Sydney.

Load testing of the 3,400-tonne main arch structure and supporting frame of the Saigon River pedestrian bridge at the factory (Photo published by VNA)

Saigon River pedestrian bridge set to be joined on October 21

The assembly comprises a main bridge structure weighing about 1,400 tonnes and a specialised steel supporting frame weighing around 2,000 tonnes. During testing, about 30 self-propelled modular transporters were used to lift the assembly 40cm off the ground for technical inspections. Sensors and monitoring equipment recorded key parameters.

Ba Vi Safari Park. (Photo: Sun Group)

Hanoi breaks ground on 299-hectare safari park

Its key features will include animal habitats modelled on natural ecosystems, veterinary and research facilities, educational exhibitions and recreational areas. Green spaces and water bodies will cover about 81.8% of the site, providing ecological corridors and suitable habitats for wildlife.

Bac Ninh launches iBacninh, a digital communication platform connecting local authorities with citizens and businesses. (Photo: VNA)

Bac Ninh launches iBacninh app to drive data-led governance

Speaking at a conference and exhibition marking National Digital Transformation Day 2026, held on October 9, Vice Chairman of the municipal People’s Committee Dao Thanh Truong stressed that digital transformation should be measured by governance efficiency, officials’ productivity and the quality of services provided to citizens and businesses.

Deputy Prime Minister Le Tien Chau addresses the meeting (Photo: VNA)

Deputy PM asks for highest education quality, safety for students

Regarding the construction of inter-level boarding schools in border communes, all 108 schools under Phase 1 opened for the 2026-2027 academic year, with 40 having completed all construction items. Procedures for groundbreaking at 121 schools under Phase 2 across 17 provinces and cities have been completed, with all projects targeted for completion before August 30, 2027.