Ministry ramps up efforts to finish key transport projects early

From the start of the year, the Ministry of Transport has been pushing forward the progress of numerous key transport projects to ensure their timely completion as planned.

du-an-1.jpg
The contractor paves asphalt for a highway project. (Photo: Viet Hung/Vietnam+)

Hanoi (VNA) - A series of critical transport projects are now in the final stages of construction, with efforts ramped up to meet the set deadlines. Additionally, newly approved projects are being expedited for investment approval and early groundbreaking, ensuring the efficient disbursement of public investment funds from the beginning of the year.

According to Le Quyet Tien, Director of the Department of Construction Investment Management, the country is aiming for a total of 3,000km of expressways. In 2025 alone, approximately 1,188km of expressways, spanning 28 projects or project components, are expected to be completed.

Among 17 projects (totaling 889km) overseen by the Ministry of Transport, 13 projects (745km) are progressing as planned, with minimal remaining obstacles.

However, four projects (144km) have yet to meet their required progress and require urgent resolution of key challenges.

For instance, the Can Tho - Hau Giang and Hau Giang - Ca Mau expressway sections (111km) need the My Thuan Project Management Board to work closely with localities to ensure sufficient sand supply, adjust design solutions, and shorten settlement waiting times.

Similarly, the 11.5km Hoa Lien - Tuy Loan Expressway requires the Ho Chi Minh Highway Project Management Board to coordinate with local authorities to complete land clearance and secure stone supplies by February 2025.

Meanwhile, for the 18km Bien Hoa - Vung Tau Expressway (Phase 2), the Project Management Board 85 must closely collaborate with local agencies to finalize land clearance and ensure a steady supply of construction stone, particularly by working with relevant authorities in Dong Nai province.

du-an-2.jpg
The Ministry of Transport races against time to complete numerous North-South and transverse expressway projects this year. (Photo: Viet Hung/Vietnam+)

In the railway sector, the Ministry of Transport is preparing investment plans for eight railway projects, including the North-South High-Speed Railway, the Ho Chi Minh City - Can Tho Railway and the Eastern Ring Railway in Hanoi.

Among these, only the Lao Cai - Hanoi - Hai Phong railway is scheduled to break ground in 2025.

At Long Thanh International Airport, key construction components are progressing according to schedule. In Package 2 (air traffic control facilities), the reinforced concrete structure of the air traffic control tower has been completed, and steel structures are now being installed. In Package 3 (essential airport facilities), the passenger terminal’s concrete structure is finished, with roof framework installation underway. Other major components, including runways, taxiways, and two connecting roads, are also being accelerated, with an overall target to achieve substantial completion by December 31, 2025.

At a progress review meeting on February 3, Minister of Transport Tran Hong Minh expressed confidence in the completion of expressway sections from Ha Tinh to Quang Tri central province. However, he raised concerns about projects in the South-Central and Mekong Delta regions, particularly the Can Tho - Ca Mau expressway and other east-west highways.

Minister Minh emphasized the need for sand embankments in the Can Tho - Ca Mau Expressway. Given the limited sand supply and time constraints, he urged authorities and research institutes to explore alternative construction methods that accelerate settlement while ensuring technical standards. He also stressed that quality management, labor safety, and environmental protection must not be compromised for the sake of progress.

du-an-3.jpg
The Ministry of Transport has prioritized the disbursement of allocated investment funds as a top political task. (Photo: Vietnam+)

Minister Minh directed project owners and relevant agencies to finalize investment procedures for urgent projects such as the Ho Chi Minh City - Trung Luong - My Thuan Expressway, the Ho Chi Minh City - Long Thanh - Dau Giay and the Cau Gie - Ninh Binh Expressway./.

See more

The Vietnam Pavilion at EXPO 2025 Osaka-Kansai. (Photo: VNA)

Vietnam pavilion opens to visitors at EXPO 2025 Osaka-Kansai

Spanning 300sqm, the pavilion showcases Vietnam’s history, culture, and innovation through modern exhibition technologies including holograms, VR, and digital mapping. Designed as a cultural gateway, it tells the story of a dynamic, inclusive, and sustainable Vietnam rooted in strong human values.

Overview of the meeting (Photo: PVdrilling.com)

Domestic oil rig demand set to soar with new projects

The PV Drilling 8 rig, newly acquired in 2024, is slated to commence operations in Vietnam by September, while PV Drilling 6 will return from overseas to serve a contract at Block B – Phu Quoc in mid-2027, positioning the company for stronger revenue growth.

The Vietnam Connect Forum 2025 takes place in Hanoi on April 23. (Photo: VnEconomy)

Vietnam remains attractive destination for foreign enterprises: forum

Over nearly four decades of Doi moi, Vietnam remains consistent in encouraging foreign investment. It has continued to create an optimal investment environment by improving its legal framework, enhancing administrative reforms, and developing infrastructure and human resources.

Checking the operation of 110kV power projects in the Central Highlands provinces. (Photo: VNA)

PM urges drastic measures to ensure power supply for peak period

It noted that as ensuring national energy security and sufficient electricity supply is one of the fundamental and decisive factors for the successful implementation of the country’s socio-economic growth targets, the Government and the Prime Minister have proactively and decisively directed relevant tasks and solutions early and from afar to ensure adequate power supply.

Vietnamese Minister of Industry and Trade Nguyen Hong Dien ̣(fourth from left) holds phone talks with US Trade Representative Jamieson L. Greer on April 23 evening. (Photo: VNA)

Vietnam, US kick start bilateral economic, trade negotiations

Vietnamese ministries and sectors stand ready to address the US’s concerns and work together to find mutually beneficial solutions based on the principle of harmonised interests and shared risks, said Minister of Industry and Trade Nguyen Hong Dien.

Deputy Prime Minister Nguyen Chi Dung speaks at the Vietnam Innovation and Private Capital Investment Forum 2025 (VIPC Summit 2025) in Hanoi on April 22. (Photo: VNA)

Deputy PM commits to innovation-driven growth at VIPC Summit 2025

Vietnam identifies sci-tech, innovation, and digital transformation as key economic drivers over the next decade, Deputy PM Dung said, noting that Vietnam’s strategic appeal to global tech giants is bolstered by a major shift in global supply chains, allowing the country to expand its manufacturing footprint in electronics, semiconductors, and AI.

A customer buys gold at a Bao Tin Minh Chau store in Hanoi (Photo: VNA)

Gold price hits new record

At 10am on April 22, Saigon Jewelry Company (SJC) listed gold bar prices at 120.5-122.5 million VND per tael.