Transport ministry calls for progress on major projects hinh anh 1The trial run of the Cat Linh – Ha Dong elevated train will commence on September 20. (Photo: VNA)

Hanoi (VNS/VNA) - Minister of Transport Nguyen Van The has ordered relevant agencies to speed up the implementation of major projects throughout the country.

The projects consist of the Cat Linh – Ha Dong Elevated Urban Railway, Tan Son Nhat International Airport and Long Thanh International Airport.

Reporting on the progress of the Cat Linh – Ha Dong Elevated Railway Project, Deputy Director of the Railway Project Management Unit Vu Hong Phuong said the train system was scheduled to start its trial run in September.

This phase was estimated to take more than three months, he said.

However, the general contractor had yet to finish and submit a detailed plan on the trial run and maintenance as well as a safety certificate for the project to the management unit, he said.

This risked delaying the project’s trial run, he added.

In response to the report, Minister The said “There is no reason for the delay in sending the detailed plan.”

He told Deputy Minister Nguyen Ngoc Dong to urgently work with the Hanoi administration, the general contractor as well as relevant agencies to resolve the situation.

The also said the maximum time for the trial run was 6 months. After the trial run, the train must be put into commercial operation.

“The project must be put into operation as soon as possible,” he said. “The more we delay the operation, the more we waste our money,”

Regarding the project to upgrade Tan Son Nhat International Airport, head of the ministry’s Planning and Investment Department Vu Duy Lam said the Airport Design and Construction Consultancy One Member Limited Liability Company and Civil Aviation Authority of Vietnam was finishing a detailed plan for upgrading the airport.

The said the plan to upgrade the airport had attracted significant public attention.

The tasked Deputy Minister Le Dinh Tho to work with the HCM City administration and relevant agencies to publish the detailed plan in early September.

The airport’s terminal 3 should be constructed as planned, he added.
Under the detailed plan, the civil aviation authority had to clearly point out the roadmap to implement the project and the sources of investment capital, he said.

For the project of building Long Thanh International Airport, The asked the civil aviation authority to consolidate the project management unit. It could hire more experts to better consult for the project.

The civil aviation authority was required to submit several options to mobilise investment capital for the project, clarifying the strengths and weaknesses of each option then submit it to the ministry and the Government for approval.-VNS/VNA
VNA