Long Thanh airport races toward commercial operation

In late January 2026, construction activities at the massive project site were in full swing under dry seasonal weather conditions. Hundreds of workers and machines were operating day and night on the second runway.

Construction underway on the passenger terminal’s jet bridge at Long Thanh Airport (Photo: nhandan.vn)
Construction underway on the passenger terminal’s jet bridge at Long Thanh Airport (Photo: nhandan.vn)

Hanoi (VNA) – After five years of construction and overcoming numerous challenges, Long Thanh International Airport officially marked a major milestone on December 19, 2025, when it welcomed its first three flights.

The country’s largest airport is now entering a decisive sprint, with all efforts focused on bringing it into full commercial operation in the first half of 2026.

In late January 2026, construction activities at the massive project site were in full swing under dry seasonal weather conditions. Hundreds of workers and machines were operating day and night on the second runway. Truong Son Corporation, one of seven contractors involved in the package, has mobilised extensive manpower and equipment, organising three shifts across four work teams to accelerate progress.

According to Dao Anh Dung, Director of the Long Thanh Airport Construction Management Board under Truong Son Corporation, the dry season has created favourable conditions for speeding up construction. Contractors are maintaining round-the-clock operations, closely adhering to progress schedules while ensuring construction quality. With the completed workload to date, the second runway is currently three months ahead of schedule compared to the contract timeline.

Meanwhile, at the passenger terminal construction and equipment installation package, structural works were largely completed by the end of 2025. The contractor consortium has now moved into the equipment installation phase. Although the contract sets a completion deadline of November 30, 2026, the involved units are determined to shorten the timeline and complete the package by June this year.

At present, contractors are conducting system integration, static installation acceptance, unloaded and loaded trial runs, and synchronised testing of imported aviation equipment.

“We are making every effort to ensure progress and quality, contributing to this national key project,” a Vinaconex engineer said, noting that the passenger terminal involves a large workload and stringent technical requirements.

According to the Long Thanh Airport Project Management Board, more than 15,000 experts, engineers and workers, along with nearly 3,000 pieces of equipment, are currently deployed across hundreds of construction fronts. All project packages have entered the final acceleration phase, coordinated around the June 2026 operational milestone to ensure system-wide synchronisation and readiness for trial operations.

During an inspection visit in mid-January, Minister of Construction Tran Hong Minh praised the efforts of the investor, consultants and contractors in maintaining progress. He urged construction units to continue intensive three-shift operations to speed up completion while strictly safeguarding quality standards. All key items must be finished before June 2026 to ensure timely airport operations as planned.

The minister also stressed the importance of external transport connectivity, calling on Dong Nai province to study and supplement additional access routes linking the airport with national highways, ring roads and the provincial transport network.

Built on more than 5,000 hectares, the Long Thanh International Airport is a three-phase project with an estimated total investment exceeding 16 billion USD. Phase one, costing over 5.4 billion USD, will have a capacity of 25 million passengers and 1.2 million tonnes of cargo annually.

Minh emphasised that Long Thanh Airport must not only be fast-tracked but also built to be green, clean and visually appealing, meeting five-star international standards when fully operational. Alongside the completion of phase one, the Ministry of Construction on January 9 assigned Airports Corporation of Vietnam as the investor for phase two, marking the next step in the airport’s long-term development plan./.

VNA

See more

Deputy Director of the E-commerce and Digital Economy Agency Hoang Ninh speaks at the E-commerce Forum 2026 (Photo: VNA)

Spring Fair 2026: E-commerce at crossroads of governance, sustainable development

Hoang Ninh, Deputy Director of the E-commerce and Digital Economy Agency under the MoIT, said the forum was organised at the very beginning of 2026 to promptly update guidance and ensure unified implementation ahead of the enforcement of new mechanisms and policies, thereby helping localities and businesses proactively prepare, ensure compliance, mitigate risks, and improve the quality of development.

PM Pham Minh Chinh and delegates kick off the first Glorious Spring Fair 2026 (Photo: VNA)

Spring Fair 2026 must become national consumer festival: PM

Ministries, agencies, units, and localities must proactively renew their mindset, shifting from merely “displaying goods” to “spreading values.” They were encouraged to use more digital tools for supply-demand matching and market regional specialties and One Commune One Product (OCOP) items to draw Vietnamese brands nearer to international friends. At the same time, they should actively hold distinctive cultural, musical, and experiential exchanges that infuse energy and deliver real value to attendees.

A trial UAV-based delivery at the Saigon Hi-Tech Park. (Photo: VGP)

Domestic firms position for booming UAV industry in Vietnam

Ho Chi Minh City’s Department of Science and Technology has recently partnered with the Management Board of Saigon Hi-Tech Park (SHTP) and technology firms to pilot UAV-based delivery services within SHTP. Though currently limited to short-distance routes, the trial represents an initial step towards integrating UAVs into daily life in Vietnam’s largest economic hub.

Prime Minister Pham Minh Chinh, Head of the National Steering Committee for the Implementation of the Politburo’s Resolution No. 79-NQ/TW on the Development of the State-owned Economic Sector, chaired the first meeting of the steering committee in Hanoi on February 1. (Photo: VNA)

PM chairs first meeting of steering committee for development of state-owned economic sector

According to the steering committee, the Politburo’s Resolution No. 79-NQ/TW on the Development of State-Owned Economic Sector was issued in the context that the whole country is striving and determined to innovate and reform in many fields, aiming to become a developing country with modern industry and upper-middle income by 2030; and a developed country with high income by 2045.

At the seminar to launch the 2 million USD initiative on green banking capacity development (Photo: VNA)

ADB, SBV launch 2 million USD green banking initiative

The initiative is a component of the technical assistance project “Inclusive and Climate Finance” funded by the Japanese Government through the Japan Fund for Prosperous and Resilient Asia and the Pacific (JFPR).

Prime Minister Pham Minh Chinh speaks at the meeting on January 31. (Photo: VNA)

PM urges flexible investment models for North–South high-speed railway

On the North–South high-speed railway, PM Chinh underscored its urgency for achieving double-digit growth, urging rapid completion of pre-feasibility and feasibility studies, parallel land clearance, and consideration of all three investment models—State, private, and PPP—ensuring balanced interests.