Major works at Long Thanh International Airport gather pace towards completion

The ACV said on July 20 that contractors are deploying additional workers and equipment to speed up construction under Component Project 3, which covers the airport's essential aviation infrastructure. Major facilities, including the first and second runways, taxiways, aircraft aprons, the passenger terminal apron and the aircraft fuel supply system, are approaching completion.

Construction of several key components of Long Thanh International Airport is entering its final stages. (Photo: VNA)
Construction of several key components of Long Thanh International Airport is entering its final stages. (Photo: VNA)

Dong Nai (VNA) – Construction of several key components of Long Thanh International Airport is entering its final stages as contractors accelerate progress to meet the project's completion schedule, according to the Airports Corporation of Vietnam (ACV).

The ACV said on July 20 that contractors are deploying additional workers and equipment to speed up construction under Component Project 3, which covers the airport's essential aviation infrastructure. Major facilities, including the first and second runways, taxiways, aircraft aprons, the passenger terminal apron and the aircraft fuel supply system, are approaching completion.

The first runway, together with its associated taxiways and aircraft parking apron, has reached nearly 91% of the contracted workload. Construction of the runway and airside taxiway system has been largely completed, while technical test flights were successfully carried out in December 2025. The package is expected to be finished by the end of July.

Construction of the passenger terminal aircraft apron has also made significant progress, with nearly 90% of the contract completed. The underground service tunnel for ground support equipment and the drainage system have already been finished, while foundation works and concrete paving have reached around 99%. Contractors are now completing concrete joint sealing, service roads, mechanically stabilised earth retaining walls, retention ponds and other supporting infrastructure. The package is scheduled for completion by the end of August.

The airport's aircraft fuel supply system has reached about 88% completion. Meanwhile, construction of the second runway and its taxiways is progressing rapidly. The runway pavement structure has been completed, and contractors are finishing the remaining concrete works. This package is expected to be completed by the end of September.

The passenger terminal, the airport's largest and most important structure, has now reached more than 67% of its contract value.

The building's structural construction is scheduled for completion in September, after which contractors will begin testing major systems and equipment, including baggage handling, baggage screening, aircraft docking guidance systems, escalators, moving walkways and elevators.

Other key facilities, including internal airport roads, technical infrastructure, airport management systems, the multi-storey car park and cargo terminal No. 1, are also being built on schedule and are expected to begin operation simultaneously by the end of the year.

According to the ACV, Component Project 3 has completed nearly 78% of the total value of signed contracts. The project's main construction packages alone have achieved nearly 58 trillion VND (about 2.2 billion USD) in completed work, equivalent to around 70% of their total contract value.

Nearly 7,200 workers are currently working on the site, and the ACV has instructed contractors to recruit an additional 2,000 personnel to ensure the airport is ready for commercial operations by the end of the year.

The ACV acknowledged that the rainy season poses significant challenges, particularly for earthworks, cement concrete paving and asphalt construction carried out outdoors.

To minimise weather-related disruptions, contractors have been instructed to implement detailed rainy-season construction plans, prioritise indoor work during periods of heavy rainfall, strengthen on-site drainage systems, install backup pumps in construction areas and adjust work schedules flexibly in response to changing weather conditions./.

VNA

See more

Tan Mingming, Deputy Director of the Foreign Affairs Office of the Dezhou Municipal People’s Government. (Photo: VNA)

Chinese firms put Vietnam on expansion radar

Tan Mingming, Deputy Director of the Foreign Affairs Office of the Dezhou Municipal People’s Government, told Vietnam News Agency reporters that the city has spent years deliberately tightening its links with the Association of Southeast Asian Nations (ASEAN), with Vietnam seen as a key partner.

A perspective of the Viettel Military Industry and Telecoms Group's high-tech semiconductor chip manufacturing plant at Hoa Lac Hi-Tech Park. (Photo: Viettel)

Hanoi builds momentum as Vietnam's semiconductor hub

As Hanoi continues to strengthen its semiconductor ecosystem, the city is creating a new growth driver for both the capital and the country, enhancing Vietnam's technological capabilities and paving the way for deeper integration into the global semiconductor value chain.

Clams are processed for export at the factory of Thanh Hoa Seafood Import-Export JSC in Thanh Hoa province. (Photo: VNA)

Vietnam steps up export to achieve 550-billion-USD target

Against a backdrop of persistent uncertainty in global commerce, the Government is implementing a broad range of measures to strengthen export growth during the remainder of the year. These include expanding overseas markets through economic diplomacy, maximising the benefits of free trade agreements (FTAs), streamlining administrative procedures, reducing logistics costs, improving access to credit and helping businesses overcome trade barriers. Authorities are also encouraging deeper processing, official cross-border exports and greater market diversification to improve the competitiveness of Vietnamese products.

A hydroponic vegetable garden in Nguyet Hoa ward operated by Green Farm Co., Ltd. (Photo: VNA)

Incentive policies for high-tech agricultural zones

Under Decree No. 263/2026/ND-CP, qualified projects are given priority to participate in State support programmes as well as funds and policies on research and development, technological innovation, technology transfer, human resource training, investment promotion and trade promotion.

Wind turbines stand fully installed at a wind power project in Gia Lai province. (Photo: VNA)

Gia Lai approves 56-million-USD wind power project

The 42MW wind farm is expected to generate about 123,780.8 MWh of electricity each year. Power generated will be transmitted to the national grid via the 220kV Pleiku 2–Krong Buk transmission line.

Garments for export to the Japanese market are produced at Hung Viet Garment Company in Hung Yen province. (Photo: VNA)

Vietnam’s garment sector pivots towards value-added growth

Future growth can no longer rely on expanding production capacity alone. Meeting this year's 48 billion USD export target will require greater productivity, higher value addition, stronger domestic sourcing, broader market diversification, and faster digital and green transformation.

Trucks carrying goods wait for customs clearance at the Thanh Thuy International Border Gate in Tuyen Quang province. (Photo: VNA)

Border economy strengthens Tuyen Quang’s growth momentum

While the stronger performance provides momentum for the province's 2026 growth target of 10.17%, officials say the focus must now shift from increasing cargo volumes to expanding services, reducing costs and retaining more value locally.

The VinFast Evo electric motorcycle on display at the event. (Photo courtesy of VinFast)

VinFast marks new step in expansion strategy in Southeast Asia

The Evo is priced at 17.5 million IDR (about 973.90 USD) in Jakarta and is available in four colour options: black, red, white and olive green. The Feliz II is sold for 18.5 million IDR, while the Viper is priced at 22 million IDR. All prices include a battery subscription package.

Passengers check in at Hanoi's Noi Bai International Airport. (Photo: VNA)

Vietnam records 15.4% growth in international air passengers

CAAV statistics show that international passenger throughput reached 26.2 million as of June 15, 2026. Of the total, Vietnamese airlines transported 9.6 million international passengers, a slight increase of 0.2% year-on-year, accounting for 36.6% of the total international passenger market.