Petrovietnam takes drastic actions to carry out Ninh Thuan 2 nuclear power project

With an urgent timeline to put the plant into operation by 2030 or 2031, the project faces significant challenges and requires a shift to a more flexible, accelerated management approach.

The design of Ninh Thuan nuclear power project released in 2016 (Source: baochinhphu.vn)
The design of Ninh Thuan nuclear power project released in 2016 (Source: baochinhphu.vn)


Hanoi (VNA) – Following the National Assembly’s approval of a resolution on special mechanisms and policies for the Ninh Thuan nuclear power project on February 19, the Vietnam Oil and Gas Group (Petrovietnam) is taking drastic actions to implement the Ninh Thuan 2 nuclear power plant project.

With an urgent timeline to put the plant into operation by 2030 or 2031, the project faces significant challenges and requires a shift to a more flexible, accelerated management approach.

Special mechanisms, policies in place

Associate Prof. Dr. Ngo Tri Long, former Director of the Price and Market Research Institute under the Ministry of Finance, noted that the approval of special mechanisms and policies for the Ninh Thuan nuclear power project will make it easier for the project’s developers to move forward. Specifically, the mechanisms allow simultaneous negotiations with international partners for construction cooperation and credit arrangements, helping to fast-track the project and avoid delays caused by prolonged administrative procedures. This will help shorten construction timelines and speed up the plant’s operational start, he held.

Additionally, the simplified contracting procedures for critical tenders will optimise time and reduce complexity, he said, adding that the flexibility to raise funds from multiple sources enables Petrovietnam to secure financing without needing approval or asset collateral. Moreover, exempting domestic banks from credit limits when financing the project is a major advantage, ensuring a steady flow of capital for its execution, Long underlined.

Meanwhile, energy expert Nguyen Thanh Son from the Electric Power University pointed out that nuclear power projects worldwide often experience significant cost overruns during construction. With an estimated 12 billion USD investment required to build a nuclear plant, there are also unpredictable operational costs, such as expenses for nuclear fuel, uranium reserves, waste disposal, and decommissioning.

He stressed the need for comprehensive government-backed guarantees to give investors confidence, citing the UK Government's studies from the 1980s and early 2000s, which found that in a free electricity market, energy companies would not build nuclear plants without governmental subsidies and guarantees.

petrovietnam.jpg
Petrovietnam's steering committee for the implementation of the Ninh Thuan 2 nuclear power project convenes its first meeting on February 10, 2025. (Photo: VNA)

Agreeing with Son, Long said that establishing contingency funds to address unforeseen challenges and securing long-term, stable electricity purchase agreements are also seen as key solutions to ensure the project's financial viability.

Petrovietnam’s quick moves

Tran Quang Dung, Permanent Deputy Secretary of Petrovietnam’s Party Committee, stated that after the Prime Minister assigned the group to work as the investor of the Ninh Thuan 2 nuclear power project, Petrovietnam has acted decisively and swiftly. The group has already submitted a report to the Ministry of Industry and Trade on the special mechanisms related to investment procedures, selection of contractors, staffing, financing, and nuclear safety standards.

The firm has established a steering committee to oversee preparations for the project. It has worked with Ninh Thuan’s provincial authorities to agree on land clearance measures for 2025 and included the project in the province’s land use planning, Dung said.

At the same time, to prepare the workforce for the nuclear power plant, Petrovietnam has sent requests to its subsidiaries to assign staff to the project and has begun receiving project documents from Vietnam Electricity (EVN) Group for review. In mid-February, Petrovietnam hosted a specialised workshop on nuclear energy to gather experts' feedback on technical and policy issues.

Petrovietnam Chairman Le Manh Hung stated that the Ninh Thuan 2 nuclear power plant is not only a crucial task entrusted by the Party and State but also an honour for Petrovietnam, aligning with the company’s goal of becoming a national energy and industrial powerhouse. With the pressing target of putting the plant into operation by 2030 or 2031, the project presents a significant challenge, and a more flexible management approach is needed to meet the deadlines, he said.

Hung said that Petrovietnam is the second-largest electricity producer in Vietnam after EVN, with extensive experiences from implementing 13 large-scale power projects. Additionally, with a BB+ credit rating independent of the government, Petrovietnam has strong financing capabilities and accumulated resources to support large energy projects. The technology for the nuclear power plant will be provided by licensed contractors under the strict supervision of the International Atomic Energy Agency (IAEA), ensuring the project’s successful implementation.

According to the baseline scenario, the Ninh Thuan 1 nuclear power plant will consist of two reactors with a capacity of 1,200 MW each, while the Ninh Thuan 2 nuclear power plant will also feature two 1,200 MW reactors./.

VNA

See more

Can Tho leaders and Bestway Group executives perform the symbolic launch ceremony for the new project. (Photo: VNA)

Bestway International launches 300 million USD plant in Can Tho city

Once operational, the plant is projected to create over 5,000 direct jobs and generate approximately 500 million USD in annual revenue, primarily through exports. The project is expected to significantly enhance regional employment and economic growth, contributing to Can Tho’s development and the broader Mekong Delta region.

Tra fish processed for export in Dong Thap province (Photo: VNA)

World Bank forecasts Vietnam's GDP growth at 5.8% in 2025

As a trade-oriented economy, with imports and exports representing almost 170% of the GDP, Vietnam is particularly exposed to ongoing shifts in global trade policies. The US remains the largest export destination of Vietnam, accounting for 30% of its total exports, while China makes up 38% of its imports.

Vietnamese Minister of Industry and Trade (MOIT) Nguyen Hong Dien (Photo: VNA)

US calls tariff talks with Vietnam productive

US Trade Representative Jamieson L. Greer and Vietnamese Minister of Industry and Trade (MOIT) Nguyen Hong Dien agreed on the importance of making swift progress towards reciprocal and balanced trade between the US and Vietnam.

The working delegation from the Party Central Committee's Commission for Information, Education and Mass Mobilisation inspects the resettlement area for residents affected by the Ninh Thuan 1 Nuclear Power Plant project. (Photo: VNA)

Ninh Thuan asked to gain public support for nuclear power plant project

Pham Van Hau, Permanent Deputy Secretary of the provincial Party Committee and Chairman of the provincial People’s Council, stated that recognising the importance of the project, the province has developed specific plans and a roadmap for its implementation. This includes focusing on effective communication efforts to gain high consensus among officials, Party members, and people.

Representatives from companies receive certificates of trademark rights at the launch of the "Green and Low-Emission Vietnam Rice" trademark. (Photo: nld.com.vn)

"Green and Low-Emission Vietnam Rice" trademark launched

VIETRISA Chairman Bui Ba Bong said that the launch is a strategic turning point in building the Vietnamese rice brand, aiming for the premium markets with strict carbon emission standards. The new rice trademark represents a commitment to environmental and social responsibility, not just a commercial label.

The Vietnam Pavilion at EXPO 2025 Osaka-Kansai. (Photo: VNA)

Vietnam pavilion opens to visitors at EXPO 2025 Osaka-Kansai

Spanning 300sqm, the pavilion showcases Vietnam’s history, culture, and innovation through modern exhibition technologies including holograms, VR, and digital mapping. Designed as a cultural gateway, it tells the story of a dynamic, inclusive, and sustainable Vietnam rooted in strong human values.

Overview of the meeting (Photo: PVdrilling.com)

Domestic oil rig demand set to soar with new projects

The PV Drilling 8 rig, newly acquired in 2024, is slated to commence operations in Vietnam by September, while PV Drilling 6 will return from overseas to serve a contract at Block B – Phu Quoc in mid-2027, positioning the company for stronger revenue growth.

The Vietnam Connect Forum 2025 takes place in Hanoi on April 23. (Photo: VnEconomy)

Vietnam remains attractive destination for foreign enterprises: forum

Over nearly four decades of Doi moi, Vietnam remains consistent in encouraging foreign investment. It has continued to create an optimal investment environment by improving its legal framework, enhancing administrative reforms, and developing infrastructure and human resources.

Checking the operation of 110kV power projects in the Central Highlands provinces. (Photo: VNA)

PM urges drastic measures to ensure power supply for peak period

It noted that as ensuring national energy security and sufficient electricity supply is one of the fundamental and decisive factors for the successful implementation of the country’s socio-economic growth targets, the Government and the Prime Minister have proactively and decisively directed relevant tasks and solutions early and from afar to ensure adequate power supply.