Unlocking wind power potential, laying groundwork for new energy era

Offshore wind diversifies supply and reduces dependence on imported fuels at a time when electricity demand is rising for industrialisation, data centres, electrified transport and green manufacturing.

Sunset over a wind farm in former Bac Lieu province, now part of Ca Mau province (Photo: VietnamPlus)
Sunset over a wind farm in former Bac Lieu province, now part of Ca Mau province (Photo: VietnamPlus)

Hanoi (VNA) – Offshore wind power is not only a source of renewable energy, but also a foundation for building a modern marine industrial ecosystem and realising the goal of making Vietnam a strong maritime nation, Assoc. Prof. Dinh Van Chau, Rector of Electric Power University, told Vietnamplus E-newspaper.

Building a modern marine industry

Reporter: Vietnam is said to have great offshore wind potential. How should this 'energy treasure' be viewed so it becomes not only a power source but also a driver of new industries and value chains?

Assoc. Prof. Dinh Van Chau: The greatest strategic advantage of offshore wind is that it creates three layers of value. These are ensuring energy security, promoting the marine economy, and enhancing national industrial capacity. If we look only at installed capacity or electricity costs, we will overlook the core value of this sector.

dai-hoc-dien-luc.jpg
Assoc. Prof. Dinh Van Chau, Rector of Electric Power University (Photo courtesy of Electric Power University)

Offshore wind diversifies supply and reduces dependence on imported fuels at a time when electricity demand is rising for industrialisation, data centres, electrified transport and green manufacturing. It is high‑density energy with good capacity factors, minimal land competition and the ability to be distributed across many sea areas. With rational planning, seasonal differences in wind across regions can complement each other and improve the system’s ability to guarantee output.

But offshore wind does not automatically ensure energy security. A large cluster tied into a weak grid or reliant on a single cable still risks widescale outages. Only when paired with appropriate transmission infrastructure, cable repair capacity, storage systems and restoration plans will offshore wind fully deliver.

It also helps the energy transition, supports net‑zero goals and can provide green power for export sectors facing tougher carbon rules. In the future, it could power green hydrogen, ammonia and synthetic fuels, green ports and coastal industrial zones, but we should not delay grid investment in the hope these markets will solve the issue.

Offshore wind is more than turbines. It can create a whole marine industrial ecosystem, from surveys and design to ports, vessels, substations, cable systems, O&M (Operation & Maintenance), finance, data services and training. Each link can become a high value‑added industry or industrial segment.

Therefore, offshore wind power should be viewed as a national industrial development programme, rather than merely a collection of individual power-generation projects.

Pioneer projects should deliver power reliably while building reusable capabilities, standard designs, trained teams, test facilities and domestic suppliers, so Vietnamese firms can join regional supply chains.

This approach aligns with Resolution No. 36-NQ/TW on Vietnam’s Sustainable Marine Economic Development Strategy, and Resolution No. 70-NQ/TW on ensuring national energy security. It also supports Resolution No. 57-NQ/TW on breakthroughs in science and technology development, innovation and national digital transformation.

Identifying development zones and creating long-term confidence

Reporter: Many believe Vietnam’s offshore wind potential is huge but remains underdeveloped. What are the core bottlenecks that should be prioritised for removal to build investor confidence and develop a transparent, stable market?

Assoc. Prof. Dinh Van Chau: First of all, we need to properly understand the concept of “potential.” The often-quoted 600 GW is technical potential, not capacity ready for immediate investment.

For an offshore wind project to become operational, it must go through numerous stages, including marine spatial planning, resource and geotechnical surveys, environmental assessment, investor selection, power purchase agreements, financing, supply chain preparation, construction and grid connection. If any link is missing, the project can be delayed.

Current bottlenecks include institutional frameworks and procedures that are out of synch. Investors need a clear, end-to-end roadmap, from survey rights and data use, sea allocation and environmental permits to pricing, power purchase agreements (PPAs) and grid connection, with transparent timelines and accountable agencies.

Resource planning is not tightly integrated with transmission planning. Cable corridors, landing points, substation land, and grid investment schedules must be defined to attract long-term capital. Revenue structures and risk allocation are also inadequate. Offshore wind requires large up-front investments, has long lead time, and faces currency and interest rate risks. Investors and lenders need contractual frameworks that specify responsibilities for delayed grid upgrades, curtailment, policy changes, and force majeure.

The domestic supply chain and system integration capacity remain limited. Vietnam needs to build simulation, testing and integration capabilities. Data and marine space management should be organised as shared infrastructure: geological, oceanographic, fisheries and environmental data must be on unified platforms with transparent sharing rules.

To build long-term confidence, priority actions include designating development zones, cable corridors and landing points. Publishing investor selection roadmaps, finalising pricing and PPA mechanisms, and alignment with resource and grid planning are also important. Other priorities include issuing technical standards for offshore wind and setting up a functional one-stop office with clear responsibility for project implementation.

Infrastructure must come first to unlock resources

Reporter: Should Vietnam shift from each project connecting individually to coordinated planning by clusters, shared collection hubs and common transmission corridors, and what principles should be set early to avoid fragmented investment and wasted infrastructure?

Assoc. Prof. Dinh Van Chau: Infrastructure should lead, but 'lead' means planning first. Offshore wind infrastructure must start with marine spatial plans, surveys, offshore grid architecture, cable corridors, landing points, connection hubs and onshore transmission plans. These should be completed before projects finalise designs and procurement.

Physical large-scale investment should match project readiness and real demand to avoid premature spending. At the start, it may be fine for each project to build its own cable and connection plan, but as deployment reaches tens of gigawatts, this creates more landing points, overlapping corridors, suboptimal grid operation and higher costs.

Vietnam should transition to coordinated planning of offshore wind clusters with shared collection centres, common cable corridors and landing points linked to the onshore 500kV transmission backbone. In the early stages, point-to-point transmission links may be used, but they should be designed for easy expansion so they can gradually evolve into a modern transmission network as the market grows.

dien-gio-nk.jpg
Wind turbines in Lam Dong province (Photo: VietnamPlus)

Planning must have a 30–50 year vision and guarantee expandability. A single empowered authority should oversee offshore grid architecture to ensure coordination across power planning, marine spatial planning, local authorities and other sectors.

Resource, grid, port, logistics and load centre planning must be developed on a common scenario and assessed from a whole system perspective. System security standards, device interoperability, responsibility allocation and cost sharing must be set from the start.

Building an integrated development ecosystem

Reporter: From international experience and Vietnam’s realities, what breakthrough package of measures is needed for offshore wind to become a pillar of the country’s energy and marine economy strategy?

Assoc. Prof. Dinh Van Chau: International experience shows that successful countries do not pursue isolated projects. They establish an integrated deployment ecosystem, including marine spatial planning, transmission infrastructure, policy frameworks, supply chains, technology, workforce development and unified governance. Vietnam should adopt the same approach.

We must finalise marine spatial planning aligned with an offshore grid architecture. That requires clearly defining priority development zones, cable corridors, landing points, collection hubs and transmission connection nodes.

It is necessary to create robust investor selection processes and power purchase agreements that will unlock capital. These mechanisms must ensure transparent developer selection, equitable risk allocation and confidence for long-term financiers.

The next priority is to mobilise private capital at large scale, using green finance, public-private partnerships and international funding, while the State focuses its investment on strategic infrastructure, high-quality data, technical standards and areas beyond what private actors can immediately deliver.

Over the long term, it is necessary to implement a national programme on developing domestic technology and supply chains with priority given to segments where Vietnam can realistically compete, such as offshore structures, substations and export cables, system integration, data and digital technologies, and engineering services. Data and human resources should be strategic infrastructure, with systematic investment in training engineers and specialists, and in testing and certification facilities for the offshore wind sector.

If one opening move is needed, select one or two pilot offshore wind clusters within 24 months and complete all conditions for investment decisions. A successful pioneer project will deliver experience, standards, data and governance models to scale up.

Vietnam should shift from ‘managing potential’ to ‘managing a portfolio of implementable projects'. Success will be measured by projects with full infrastructure, financing, contracts and supply chains ready to operate on schedule. Then offshore wind can become a pillar of energy security, the marine economy and national development.

Reporter: Thank you very much!

VNA

See more

The conference is jointly organised by the Ho Chi Minh City Investment and Trade Promotion Centre (ITPC), the Australian Consulate General in Ho Chi Minh City, the Vietnam Trade Office in Australia and the Australian Chamber of Commerce Vietnam (AusCham) on September 30. (Photo: VNA)

Vietnamese businesses advised to compete on quality in Australian market

Australia has strong purchasing power and diverse demand for Vietnamese products, from industrial goods, machinery and equipment, textiles and footwear to wood products, agricultural and aquatic products and processed food. Two-way trade reached 9.79 billion USD in the first seven months of 2026, up 20% year-on-year, while Vietnam’s exports to Australia surged 30%.

The Ministry of Industry and Trade holds the first meeting of the GoGlobal Steering Committee in Hanoi on September 30 to review implementation and set key tasks for the programme. (Photo: VNA)

Vietnam sets roadmap to take businesses global

GoGlobal aims to support the private sector in establishing a stronger, more effective and sustainable presence in foreign markets. By 2030, the programme targets training at least 10,000 businesses, providing internationalisation consulting to 1,000, supporting 100 firms in overseas investment, and helping 100 businesses join regional or global value chains.

Content creators help farmers sell longan and OCOP products on TikTok. (Photo: VNA)

Tighter livestream controls to curb counterfeit goods online

Under the stricter process, checks now cover not only products but also sellers, businesses, promotional content and livestream participants. Content creator and affiliate marketer Vo Truong Duy said that sellers are required to provide products and relevant documents for verification before livestreams. Information on distributors, product declarations, labels and ingredients must be consistent.

Petrolimex Aviation supplies SAF for Vietjet flights (Photo: baochinhphu.vn)

Vietnam studies ways to broaden use of sustainable aviation fuel

The proposed SAF roadmap will take into account Vietnam's international commitments, the Carbon Offsetting and Reduction Scheme for International Aviation (CORSIA) and the country's ability to develop a domestic SAF supply while avoiding shocks to domestic airlines and the air transport market.

Fishing boats anchor before heading out to the sea. (Illustrative photo: VNA)

An Giang tightens management of high-risk violators to combat IUU fishing

Vice Chairman of the People’s Committee of An Giang province Ngo Cong Thuc asked relevant departments, agencies, forces and local authorities to manage all fishing vessels ineligible for operation, regularly update their status and anchorage locations, and ensure that no such vessels engage in fishing activities.

Nguyen Thi Ngoc Hue, Senior Director of Human Resources Strategy and Brand at Aeon Vietnam, speaks at an event. (Photo: Aeon Vietnam)

Japan's retail giant Aeon Corporation bets big on Vietnamese market

Under its medium-term business plan through March 2031, Aeon aims to generate more than 300 billion JPY (1.9 billion USD) in operating revenue in Vietnam, 2.5 times higher than its fiscal year 2026 forecast. The group plans to increase its supermarket network, including MaxValu, from about 60 stores to 300, while allocating about 60% of its Southeast Asian investment to Vietnam.

At a working session between Phu Tho's leaders and the Opora Rossii delegation. (Photo: VNA)

Phu Tho courts Russian investors in vocational training, trade

Vice Chairman of the Phu Tho provincial People’s Committee Nguyen Khac Hieu has expressed a desire to strengthen connections with Russian partners in areas such as education, industrial growth, agro-forestry processing, technology, and trade.

At the signing ceremony of a memorandum of understanding on cooperation between VinFast and HS Hyosung. (Photo: VNA)

RoK group adds 100 million USD investment in Da Nang

Covering about 11 hectares, the project will manufacture BCF yarn, commercial carpets and automotive floor carpets, with an annual capacity of 16,800 tonnes of BCF yarn and approximately 7.8 million sq.m of carpets.

Vietnamese Minister of Industry and Trade Le Manh Hung (left) and Canadian Minister of Energy and Natural Resources Tim Hodgson at their talks. (Photo published by VNA)

Vietnam, Canada open new avenues for energy cooperation

Minister of Industry and Trade Le Manh Hung recently held talks with Canadian Minister of Energy and Natural Resources Tim Hodgson, focusing on implementing the newly signed memorandum of understanding on energy and clean energy transition cooperation.